M&M employs a dedicated team of underground utility specialists experienced in the intricracies of subgrade construction.

Project: CSO Phase D - Sault Ste. Marie, Michigan
Description: Part of the State's mandate to separate storm and sanitary lines, over 60,000 linear feet of new storm sewer, water main and sanitary sewer lines stretching over 45 city blocks. Entire roads were reconstructed including sand subbase, gravel, curb and gutter; hauling out 100,000 cubic yards of clay and replacing it with clean sand.
Kudos: This project was the fourth phase for the City of Sault Ste, Marie; M&M was the only contractor to complete the phase on schedule.
Owner: City of Sault Ste. Marie
Engineer: Wilcox Associates, Inc.
Value of Contract: $8,400,000
Project: West Portage Avenue - Sault Ste. Marie, Michigan
Description: Nearly 1 mile of road reconstruction and road realignment including storm sewer, sanitary sewer, and watermain construction. Partically funded by Homeland Security to improve border crossing facilities.
Owner: MDOT
Engineer: Wilcox Associates, Inc.
Value of Contract: $2,200,000
Project: Harrison Collection, Division I - Harrison, Michigan
Description: Approximately 175,000 cubic yards of earth excavation, embankment, and sand cover for the construction of four lagoons. 75,000 cubic yards of clay placement to contruct three foot clay liner. PVC Liner and irrigation piping.
Owner: City of Harrison
Value of Contract: $1,700,000